Pengaruh Fungsi Manajemen POAC terhadap Kinerja Proyek Peningkatan Jaringan Irigasi Sebulu Modern, Kabupaten Kutai Kartanegara
Keywords
Construction Management, Irrigation Network, POAC, Project Performance, Multiple Linear RegressionAbstract
Irrigation network improvement projects are strategic public works for food security, yet their delivery often suffers from delays, cost deviations, and quality problems rooted in weak project management. Indonesian studies of construction management functions focus mostly on building projects, leaving water-resources infrastructure in East Kalimantan under-examined. This study analyses the influence of Planning, Organizing, Actuating, and Controlling (POAC) on the performance of the Sebulu Modern Irrigation Network Improvement Project, Kutai Kartanegara Regency, delivered by the East Kalimantan Provincial Public Works Agency and its contractor. An explanatory quantitative design was applied. Data from 51 purposively selected respondents were collected through a 24-item six-point Likert questionnaire and analysed using validity and reliability tests, classical assumption tests, multiple linear regression, and effective-contribution analysis in SPSS 30. The four functions jointly explained 81.0% of the variance in project performance (F = 49.020; p < 0.001). Planning (β = 0.438; p < 0.001), organizing (β = 0.333; p = 0.001), and actuating (β = 0.291; p = 0.002) had significant positive effects, whereas controlling was not significant (β = 0.075; p = 0.614) despite having the strongest bivariate correlation (r = 0.820). Planning provided the largest effective contribution (32.6%). The non-significance of controlling is attributed to its high overlap with the other functions (tolerance = 0.191), suggesting that supervision operates as an embedded administrative routine rather than an independent performance driver. Public irrigation projects should therefore prioritise front-end planning and clear inter-party organisation, while redesigning controlling into an indicator-based early-warning system.
References
Albar, R. F., & Johari, G. J. (2023). Evaluasi kinerja manajemen konstruksi proyek pembangunan kantor dinas kesehatan. Jurnal Konstruksi, 21(2), 249–256. https://doi.org/10.33364/konstruksi/v.21-2.1409
Amir. (2021). Evaluasi kinerja konsultan pengawas pada proyek pembangunan jalan di Provinsi Kalimantan Timur. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil, 4(1), 1–9. https://doi.org/10.31602/jk.v4i1.5112
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342. https://doi.org/10.1016/S0263-7863(98)00069-6
Chan, A. P. C., Scott, D., & Chan, A. P. L. (2004). Factors affecting the success of construction projects. Journal of Construction Engineering and Management, 130(1), 153–155. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(153)
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479–489. https://doi.org/10.1016/j.ijproman.2011.10.004
Dwiretnani, A., Dony, W., & Manalu, F. A. (2024). Analisis kinerja konsultan pengawas dalam pelaksanaan proyek konstruksi. Jurnal Civronlit Unbari, 9(1), 1–12. https://doi.org/10.33087/civronlit.v9i1.112
Esther, R. A., Saragih, J. R., & Harahap, M. A. K. (2025). Evaluasi kinerja jaringan irigasi Daerah Irigasi Panombean/Pane Tongah di Kabupaten Simalungun. Jurnal Regional Planning, 7(1), 32–37. https://doi.org/10.36985/8rh8j130
Febrianti, D., Mawardi, E., Farizal, T., Zakia, Z., Willis, R., & Elviani, E. (2025). Prioritas rehabilitasi jaringan irigasi di Jeuram menggunakan Analytical Hierarchy Process (AHP) untuk mengoptimalkan produktivitas pertanian. VOCATECH: Vocational Education and Technology Journal, 7(2), 282–296. https://doi.org/10.38038/vocatech.v7i2.243
Ghozali, I. (2018). Aplikasi analisis multivariate dengan program IBM SPSS 25 (Edisi 9). Badan Penerbit Universitas Diponegoro.
Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2019). Multivariate data analysis (8th ed.). Cengage Learning.
Indramanik, I. B. G., Silvi, N. P., Wiradnyana, I. G. O., & Da Cunha, F. Y. C. (2024). Analisis kinerja manajemen konstruksi pada proyek pembangunan gedung pelayanan kesehatan ibu dan anak RSUP Prof. Dr. I Goesti Ngoerah Gde Ngoerah. Ganec Swara, 18(4), 2462–2472. https://doi.org/10.35327/gara.v18i4.1199
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83–94. https://doi.org/10.1080/014461997373132
Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2020). Rencana strategis Kementerian Pekerjaan Umum dan Perumahan Rakyat tahun 2020–2024. Kementerian PUPR.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.
Kurniyaningrum, E., Mulya, H. D., & Anwar, S. (2023). Evaluasi kesiapan modernisasi sistem irigasi di Daerah Irigasi Molek berdasarkan indeks kinerja. Jurnal Sainstek STT Pekanbaru, 11(2), 228–233. https://doi.org/10.35583/js.v11i2.211
Rasa, B. T., & Handayani, K. D. (2023). Evaluasi kinerja proyek konstruksi ditinjau dari aspek biaya dan waktu menggunakan metode Earned Value Analysis, studi kasus: Pembangunan gedung perkantoran Balai Besar Wilayah Sungai (BBWS) Bengawan Solo. Portal: Jurnal Teknik Sipil, 15(2), 12–19. https://doi.org/10.30811/portal.v15i2.4619
Republik Indonesia. (2019). Undang-Undang Republik Indonesia Nomor 17 Tahun 2019 tentang Sumber Daya Air. Lembaran Negara Republik Indonesia Tahun 2019 Nomor 190.
Robbins, S. P., & Coulter, M. (2018). Management (14th ed.). Pearson.
Sahid, M. N., Setiyaningsih, I., Solikhin, M., & Salam, A. (2019). Analisis faktor-faktor penyebab pembengkakan biaya oleh kontraktor pada proyek jalan APBD Kota Solo tahun 2017–2018. Prosiding Simposium Nasional RAPI XVIII, 199–208. https://proceedings.ums.ac.id/rapi/article/view/1370
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Soeharto, I. (1999). Manajemen proyek: Dari konseptual sampai operasional (Jilid 1, Edisi 2). Erlangga.
Sugiyono. (2023). Metode penelitian kuantitatif, kualitatif, dan R&D. Alfabeta.
Terry, G. R., & Rue, L. W. (2019). Dasar-dasar manajemen (Edisi revisi). Bumi Aksara.
Yusna, S. N. (2025). Analisis kinerja manajemen konstruksi pada proyek gedung di Perguruan Tinggi XYZ. KERN: Jurnal Ilmiah Teknik Sipil, 11(1), 17–26. https://doi.org/10.33005/kern.v11i1.68
Yusuf, M., & Nurdiyanto, N. (2025). Analysis of operational and maintenance performance of Cimedang–Ciputrapinggan Service Unit (SUP) Merjan Irrigation Area, Pangandaran Regency. Journal of World Science, 4(2), 270–282. https://doi.org/10.58344/jws.v4i2.1307